AHS Active
42
RAB Baseline
IDR 18.74B
Labor Portion
24.8%
Cost Variance
+3.6%
AHS Code
Work Item
UoM
Harga Satuan
AHS/STR/0008Beton K-300 Kolom Lantai 2m3IDR 1,482,500
AHS/STR/0007Pembesian D16 Struktur BalokkgIDR 18,950
AHS/ARC/0014Pasangan Dinding Bata Ringan 10 cmm2IDR 165,300
AHS/ARC/0015Plester Aci Interiorm2IDR 72,400
AHS/MEP/0021Instalasi Conduit ElektrikalmIDR 54,800
AHS/EXT/0004Galian Tanah Manualm3IDR 98,600

AHS Detail

Cost Component Breakdown

Type
Resource
Coefficient
UoM
Unit Price
Amount
MaterialReady Mix Concrete K-3001.0200m3IDR 1,120,000IDR 1,142,400
LaborTukang Beton0.1800OHIDR 185,000IDR 33,300
LaborPekerja Cor0.4200OHIDR 145,000IDR 60,900
EquipmentConcrete Pump0.0550hourIDR 1,750,000IDR 96,250
OverheadSite Overhead Allocation8.0000%%IDR 1,332,850IDR 106,628

Calculated Unit Price

IDR 1,142,400
IDR 94,200
IDR 96,250
IDR 106,628
IDR 1,482,500 / m3